Oklahoma State University: The STATE's University
Visit the OSU Home Page

Approved FY06 Projects

 
Project Description Approved Budget YTD Expended Balance Status
Multimedia equipment for General University Classrooms $382,888.00 $382,888.00 $0.00 Completed
Computer Lab Rotation $117,500.00 $74,149.20 $43,350.80 In Progress
Server Rotation and Testing Environment $75,000.00 $44,603.83 $30,396.17 In Progress
Assistive Technology $57,500.00 $19,525.05 $37,974.95 In Progress
Disk Storage and Enhanced Backup Capabilities $200,000.00 $200,000.00 $0.00 Completed
Virtual Labs $150,000.00 $60,160.91 $89,839.09 In Progress
Computer Lab Rotation - College of Agriculture $88,500.00 $83,485.00 $5,015.00 Completed
 
Last Updated: 09/29/06
 
The State's University
Oklahoma State University - Stillwater | Stillwater, OK 74078 | 405.744.5000
Copyright © 2006 Oklahoma State University | All rights reserved